Equipment
Excavator Daily Inspection Checklist: Pre-Start Checks
- Frequency
- Daily
- Completed by
- Excavator operator
- Approved by
- Site supervisor or plant manager
- The checklist
- 39 checks · 6 sections
An excavator daily inspection checklist is the operator's pre-start check of a hydraulic excavator: a walk-round for leaks, cracks and loose parts, the quick hitch, the cab and its safety devices, a short function test, and the work area. The operator completes it before starting work each day, and again when the machine or the attachment changes.
In Türkiye, the Regulation on the Use of Work Equipment (Annex III, 1.3) requires operators to check work equipment before each start of work, to record the visual and function check, and to take equipment with a crack or excessive wear out of use. Hydraulic excavators are also subject to periodic control at least once a year (Annex III, Table 6). In the US, OSHA 29 CFR 1926.20(b) requires frequent and regular inspections of equipment by competent persons and bans the use of unsafe machinery. In the UK, HSE asks for a programme of daily visual checks, regular inspections and servicing, and for safety-critical defects to take the excavator out of service.
This form does not replace the manufacturer's manual, the periodic control or thorough examination, or the checks on the excavation itself. For those, use the excavation safety checklist. For the rest of the site, see the construction site safety inspection guide.
How to use this checklist
- Complete the form before the first start of the day, with the machine parked on level ground, the bucket lowered and the engine off.
- Walk round the machine first, then check the cab and safety devices, then start the engine and test the controls, travel and brakes.
- Check the work area last: buried services, overhead lines, ground, edges and the people who will work near the machine.
- Mark each check Pass, Fail or N/A, describe every defect in the notes and photograph physical damage.
- If a critical check fails, do not operate the excavator: remove the key, tag the machine out of service and tell your supervisor.
- Sign the form and keep it with the machine's inspection and maintenance records.
The checklist: Excavator Daily Inspection Checklist: Pre-Start Checks
Inspection details
Operator and documents
- 2.
The periodic control or thorough examination is in date and the last report allows the machine to be usedCritical
Türkiye: at least yearly for hydraulic excavators, and the last report travels with a mobile machine used off the premises. UK: a quick hitch is thoroughly examined under LOLER every 12 months if it stays on the machine, every 6 months if it does not.
PassFailN/A - 3.
The operating instructions are kept with the machine
Ref.: [1]
PassFailN/A
Walk-round (engine off)
Machine parked on level ground, bucket or attachment lowered to the ground.
- 4.
No oil, fuel or coolant is leaking under the machine or in the engine and pump compartments
PassFailN/A - 5.
Hydraulic hoses, pipes and connections are undamaged, and the boom, arm and bucket cylinders show no leaks or damageCritical
Look for cuts, bulges, rubbing and wet fittings. Never feel for a leak with your hand.
PassFailN/A - 6.PassFailN/A
- 7.
The bucket or attachment, its linkage and pins are secure, undamaged and free of packed dirt and stones
Check tooth and cutting edge wear against the limits in the manual.
PassFailN/A - 8.
The quick hitch is fully locked onto the attachment and, where the hitch uses one, the manufacturer's retaining pin is in placeCritical
Check from the ground if you cannot see the hitch clearly from the cab. Never replace the pin with a bolt, wire or other substitute. Repeat after every attachment change. Mark N/A if no quick hitch is fitted.
PassFailN/A - 9.
Tracks, shoes and track drive (or tyres and wheel nuts) are undamaged, with no loose or missing bolts
Check track tension or tyre pressure as the manual describes.
PassFailN/A - 10.
The frame, superstructure and counterweight are undamaged, and doors, covers and guards are in place and closed
PassFailN/A - 11.
Engine oil is between the minimum and maximum marks, and the other levels the manual lists for the daily check are in range
Drain the fuel water separator if the display shows it is full, and check that the radiator and coolers are not clogged.
PassFailN/A - 12.
Steps, handholds and walkways are secure and free of mud, oil and ice
Ref.: [1]
PassFailN/A
Cab and safety devices
- 13.PassFailN/A
- 14.
Mirrors and cameras are fitted, clean, undamaged and adjusted, and the camera screen worksCritical
PassFailN/A - 15.
The cab and its protective structure are undamaged
The cab protects the operator if the machine rolls over or an object falls on it.
PassFailN/A - 16.PassFailN/A
- 17.
With the safety (hydraulic lock) lever in the locked position, the boom, arm, bucket, swing and travel controls do not move the machineCritical
PassFailN/A - 18.
The horn works and can be heard over the site noise
Ref.: [1]
PassFailN/A - 19.
The travel or reversing alarm and the warning beacon work
In Türkiye, audible and visual reversing warnings must work during reversing. OSHA's earthmoving equipment rule asks for a reverse alarm or a signaller when the view to the rear is obstructed.
PassFailN/A - 20.
Work lights and travel lights work
Mark N/A only if the machine works in daylight and has no lights fitted.
PassFailN/A - 21.
A fire extinguisher is on the machine or close to where it works, charged and within its service date
PassFailN/A - 22.PassFailN/A
Function test (engine running)
Make sure nobody is near the machine before you start the engine.
- 23.PassFailN/A
- 24.
The boom, arm, bucket and swing respond smoothly to the controls and stop when the controls are releasedCritical
Stop if a movement is jerky, slow or creeps.
Ref.: [1]
PassFailN/A - 25.
The machine travels and steers in both directions and the brakes stop and hold itCritical
Test on a clear, level area with nobody nearby.
PassFailN/A - 26.
There is no unusual noise, vibration, smoke or smell from the engine or hydraulics
Ref.: [1]
PassFailN/A
Work area and lifting
- 27.
Underground cables, gas, water and sewer lines in the digging area have been located and markedCritical
PassFailN/A - 28.
Overhead power lines near the work have been identified and the machine is kept at a safe distance by barriers or warning signsCritical
Allow for the full reach of the boom and for wire sway in wind. US: at least 10 feet (3.05 m) from lines rated 50 kV or below (OSHA 1926.600(a)(6)). The Turkish regulation gives no figure; get the distance from the line operator. Mark N/A if there are no lines.
PassFailN/A - 29.
The ground can carry the machine, and the machine is kept back from excavation edges, slopes and waterCritical
Where the operator cannot see the edge clearly, use barricades, stop logs or a signaller.
PassFailN/A - 30.
People are kept out of the excavator's working and slewing area by barriers, signs or a marked exclusion zoneCritical
PassFailN/A - 31.
There is clear space between the slewing superstructure and any wall, vehicle or other fixed obstruction
HSE asks for a clearance of over 0.5 m between any part of the machine, particularly the counterweight, and the nearest obstruction. Fence the gap off where this cannot be kept.
PassFailN/A - 32.
Where the operator's view is restricted, a trained signaller is in place and the signals are agreed
The signaller stands in a safe position where the operator can see them. Mark N/A if the operator has a clear view of the whole working area.
PassFailN/A - 33.PassFailN/A
- 34.PassFailN/A
- 35.
If the excavator will lift loads, the maximum load for this configuration is marked on the machine and the lift is planned and supervisedCritical
Mark N/A if the machine will not be used for lifting today.
Ref.: [1]
PassFailN/A - 36.
Slings, shackles and other lifting accessories are marked with their capacity, undamaged and within their examination date
UK (LOLER): lifting accessories are thoroughly examined every 6 months unless an examination scheme says otherwise. Türkiye: at least yearly. Mark N/A if no lifting is planned.
PassFailN/A
Result
Critical check: if it fails, stop and correct it before work continues.
Sign-off
Operator
Supervisor
Run this checklist on your phone
FindRisk turns inspections into a few taps: AI-generated checklists you can edit and save as templates, photo markup with AI hazard analysis, Fine-Kinney risk scoring and an instant PDF report.
Download FindRiskLegal basis and references
- [1] Türkiye: İş Ekipmanlarının Kullanımında Sağlık ve Güvenlik Şartları Yönetmeliği (Resmî Gazete, 25.04.2013, 28628; son değişiklik 23.12.2025, 33116) — Annex III 1.3–1.3.2: operator check before each start of work, daily visual and function check, recorded; cracked or badly worn equipment out of use. Annex III 1.9, 2.6 and Table 6: periodic control of hydraulic excavators at most yearly. Annex I 2.1–2.17, 3.1.4, 3.1.6, 3.1.7, 3.2.2; Annex II 1.1, 2.1–2.4, 3.1.1, 3.1.3, 3.2.5; Articles 7, 8, 10, 11.
- [2] Türkiye: Yapı İşlerinde İş Sağlığı ve Güvenliği Yönetmeliği (Resmî Gazete, 05.10.2013, 28786) — Annex 4: item 15 (power lines), items 49–57 (excavation and material-handling machines: condition, trained users, periodic control, ground, signaller, movement areas, reversing warnings, falling into the excavation, cab protection, operator only), items 62(b), 68 and 71 (buried services, distance from the edge, workers kept out of the machines' movement area).
- [3] Türkiye: ÇSGB İş Sağlığı ve Güvenliği Genel Müdürlüğü, Güvenli İnşaat Bilgi Kartı 1: Ekskavatör, Temel Hususlar — Operators hold an operator certificate and are trained; the limits of the working area are known and unauthorised entry is prevented with barriers and signs; operators are encouraged to report faults.
- [4] United States: OSHA 29 CFR 1926.20, General safety and health provisions — (b)(2) frequent and regular inspections of equipment by competent persons; (b)(3) unsafe machinery tagged or locked out of use, or removed; (b)(4) only employees qualified by training or experience operate equipment.
- [5] United States: OSHA 29 CFR 1926.600, Equipment — (a)(3) buckets and similar equipment lowered or blocked when not in use, parking brake set; (a)(5) cab glass with no visible distortion; (a)(6) clearance from power lines, 10 feet for lines rated 50 kV or below.
- [6] United States: OSHA 29 CFR 1926.602, Material handling equipment — Rules for earthmoving equipment (the list in (a)(1) ends with "and similar equipment" and does not name excavators): (a)(4) service brakes able to stop and hold the equipment; (a)(9)(ii) reverse signal alarm or a signaller where the view to the rear is obstructed.
- [7] United States: OSHA 29 CFR 1926.651, Specific excavation requirements — (b) underground utility installations located before digging; (e) no employee underneath loads handled by lifting or digging equipment; (f) warning system where mobile equipment works next to an excavation edge the operator cannot see.
- [8] United Kingdom: HSE, Excavators: Overview — Exclusion with barriers, clearance of over 0.5 m when slewing, visibility aids, plant and vehicle marshaller, bucket attachment; trained, competent and authorised drivers; daily visual checks, defect reporting, safety-critical defects take the excavator out of service.
- [9] United Kingdom: HSE, Industry guidance on quick hitches — Retaining pin available and checked before work; check from the ground if the hitch cannot be seen from the cab; no substitute pins; nobody working below the bucket; LOLER thorough examination every 12 months for a hitch that stays on the machine, 6 months otherwise.
- [10] United Kingdom: HSE, Inspection of work equipment (PUWER regulation 6) — Quick checks before use, such as functional testing of brakes and lights on mobile machinery; the condition of windows, mirrors and CCTV on mobile plant; who can inspect; when records are needed.
- [11] United Kingdom: HSE, Mobile work equipment (PUWER Part III) — Roll-over risk, restraint systems, preventing start-up by unauthorised people, braking and stopping device, devices for improving driver vision, lighting, fire-fighting equipment.
- [12] United Kingdom: HSE, Traffic management on site — Mirrors, CCTV cameras and reversing alarms as aids for drivers; trained plant and vehicle marshallers; signallers trained and authorised.
- [13] United Kingdom: HSE, Thorough examinations and inspections of lifting equipment (LOLER) — Thorough examination every 6 months for lifting accessories and 12 months for other lifting equipment unless an examination scheme says otherwise; simple pre-use checks by users.
- [14] International: Volvo Construction Equipment, Keep Your Excavators Running Their Best with This Prestart Checklist (2020) — Manufacturer guidance, used as good practice: engine oil level, water separator, leaks, hydraulic lines and cylinder mountings, boom and arm cracks, bucket linkage, track chain and shoes, frame and covers, coolers, mirrors and cameras, seat belt, safety lever. Your machine's own manual comes first.
Version 1 · Updated November 26, 2026 · findrisk.net/checklists/excavator-daily-inspection-checklist/
Fill in this checklist on your phone. Scan to download FindRisk: run the checklist, add photos, score risks and share a PDF report in minutes.
Version 1 · Updated November 26, 2026 · findrisk.net/checklists/excavator-daily-inspection-checklist/
Frequently asked questions
How often should an excavator be inspected?
Every day before work starts, and at longer intervals by a qualified person. In Türkiye, Annex III of the Regulation on the Use of Work Equipment requires an operator check before each start of work and a periodic control of hydraulic excavators at least once a year, unless the standard sets another interval. HSE in the UK asks for daily visual checks, regular inspections and servicing schedules.
Who carries out the daily excavator inspection?
The operator. The Turkish regulation says the visual and function check is done by the operator or by a person who knows the equipment and how it works. HSE says equipment can be inspected by anyone with sufficient knowledge and experience of it, and that drivers should be encouraged to report defects.
What should I do if I find a defect during the check?
Report it at once. HSE says reported problems should be put right quickly and the excavator taken out of service if the item is safety critical. The Turkish regulation requires equipment with a crack or excessive wear to be taken out of use, and OSHA 1926.20(b)(3) requires unsafe machinery to be tagged or locked out of use, or removed from the site.
Does the daily check have to be written down?
It depends on the country. In Türkiye, Annex III (1.3.2) of the Regulation on the Use of Work Equipment says the operator's visual and function check is recorded. HSE's guidance on PUWER says records are not normally required for the simplest pre-use checks, but a written check makes defects easier to follow up.
How do you check a quick hitch before work?
Confirm that the attachment is locked and, on hitches that use one, that the manufacturer's retaining pin is in place. HSE's guidance says the operator must check from the ground if the hitch cannot be seen clearly from the cab, and that bolts, wire or other substitutes must never replace the pin. Repeat the check after every attachment change.