Sling Inspection Checklist: Pre-Use Lifting Accessory Checks
Adapt this checklist to your site: edit, add, remove and reorder the checks, add your company name and logo, then save it as a PDF. Nothing is uploaded; your changes stay in this browser.
Your form
Inspection details (blank fields on the form)6 fields
The checklist · 32 checks · 5 sections
Sign-off (who signs the form)2 signers
FindRiskfindrisk.netSling Inspection Checklist: Pre-Use Lifting Accessory Checks
Inspection details
Identification and records
- 1.
The accessory carries a legible tag or marking showing its rated capacityCritical
No legible marking means the accessory is not used.
Ref.: [1] [3] [4]
PassFailN/A - 2.
The marking shows the details needed for its type
Chain: size, grade, rated capacity, reach. Wire rope: safe working load for the hitch, the angle it is based on, number of legs. Synthetic web: rated capacity per hitch and the material.
Ref.: [1] [2] [3]
PassFailN/A - 3.
The latest periodic inspection or thorough examination is recorded and not overdueCritical
Türkiye: authorised person, yearly unless the standards set another interval. UK: thorough examination every 6 months unless an examination scheme says otherwise. US: chain slings at least every 12 months, with a record.
Ref.: [3] [4] [1]
PassFailN/A
Visual checks for every accessory
- 4.
The sling is not shortened or joined with knots, bolts or makeshift linksCritical
Ref.: [1] [2]
PassFailN/A - 5.
The sling legs are not kinkedCritical
Ref.: [1]
PassFailN/A - 6.
Hooks have no cracks, and are not opened out or twistedCritical
OSHA removes hooks opened more than 15% of the normal throat opening (narrowest point) or twisted more than 10° from the plane of the unbent hook. A safety latch, where fitted, should close the opening.
Ref.: [1]
PassFailN/A - 7.
Master links, coupling links, end fittings, shackles and eyebolts have no cracks, bending or other deformationCritical
The daily check covers the sling and all its fastenings and attachments. Shackles must also show their working load limit.
Ref.: [1] [2] [3]
PassFailN/A - 8.
There is no sign of heat damage (discolouration, melting, charring)Critical
OSHA limits: chain slings removed if heated above 1000 °F; fibre-core wire rope above 200 °F; nylon and polyester webbing not used above 180 °F.
Ref.: [1]
PassFailN/A
Checks by accessory type
Complete only the block for the accessory's type and mark the others N/A.
- 9.
Chain: no cracked, deformed or stretched links and no defective weldsCritical
Lay the chain out straight and look along it for links that are longer, bent or nicked.
Ref.: [1]
PassFailN/A - 10.
Chain: link wear is within the allowed limitCritical
OSHA Table N-184-1 gives the minimum size at any point of a link (e.g. 25/64 in for 1/2 in chain). Otherwise use the manufacturer's wear limits.
Ref.: [1] [2]
PassFailN/A - 11.
Wire rope: fewer than 10 broken wires in one rope lay and fewer than 5 in one strand in one layCritical
Removal criterion in OSHA 1910.184(f)(5)(i): ten randomly distributed broken wires in one rope lay, or five broken wires in one strand in one rope lay.
Ref.: [1]
PassFailN/A - 12.
Wire rope: outside wires are not worn or scraped by a third of their original diameterCritical
Ref.: [1]
PassFailN/A - 13.
Wire rope: no kinking, crushing, bird caging or other distortion of the ropeCritical
Ref.: [1]
PassFailN/A - 14.
Wire rope: no corrosion of the rope or its end attachmentsCritical
Ref.: [1]
PassFailN/A - 15.
Wire rope: eyes are not formed with wire rope clips or knots, and protruding strand ends at splices are covered or bluntedCritical
Ref.: [2]
PassFailN/A - 16.
Synthetic sling: no snags, punctures, tears or cutsCritical
For round slings, also check the cover and follow the manufacturer's discard criteria.
Ref.: [1]
PassFailN/A - 17.
Synthetic sling: no broken or worn stitchesCritical
Ref.: [1]
PassFailN/A - 18.
Synthetic sling: no acid or caustic burnsCritical
Nylon is not used near acids or phenolic fumes; polyester and polypropylene not near caustics.
Ref.: [1]
PassFailN/A - 19.
Fibre rope: no abnormal wear, broken or cut fibres, powdered fibre between strands, uneven strands, discolouration or rotCritical
Repaired or reconditioned fibre rope slings are not used.
Ref.: [1]
PassFailN/A
Rigging the load
- 20.
The accessory suits the load, its lifting points, the connecting parts and the conditions (heat, chemicals, weather)Critical
Ref.: [3] [1]
PassFailN/A - 21.
The load is within the capacity marked for the hitch and leg angle being usedCritical
Capacity changes with the hitch (straight, choke, basket) and falls as the leg angle widens; read the value for this configuration.
Ref.: [1] [4]
PassFailN/A - 22.
Hooks, rings, links and shackles in the set are rated at least as high as the sling, or the set is used at its weakest part's ratingCritical
Ref.: [1] [2]
PassFailN/A - 23.
The sling is padded or protected where it passes over sharp edges of the loadCritical
Ref.: [1]
PassFailN/A - 24.
The sling is securely attached and basket hitch loads are balanced so they cannot slipCritical
Ref.: [1]
PassFailN/A - 25.
Hands and fingers are kept out from between sling and load while the sling is tightened
Ref.: [1]
PassFailN/A - 26.
No one is under the load or in its path, and loads will not pass over unprotected workplacesCritical
Ref.: [1] [3]
PassFailN/A - 27.
The accessory is not used to lift people unless it is provided for that purposeCritical
Ref.: [3]
PassFailN/A - 28.
The load will be taken up without shock loading, and the sling will not be pulled from under a resting load
Ref.: [1] [2]
PassFailN/A
Result
- 29.
Every defect found has been reported in writing to the lifting supervisor
Ref.: [4] [1]
YesNoN/A - 30.
Any accessory that failed a critical check has been removed from service and tagged or quarantinedCritical
Do not repair slings on site: OSHA allows repairs only by the manufacturer or an equivalent entity, and bans repaired fibre rope slings.
Ref.: [1] [2]
YesNoN/A - 31.
After use, accessories are stored where they cannot be damaged and are kept out of the immediate work area
Ref.: [3] [2]
PassFailN/A - 32.
Notes and defects found
Note: ________
Critical check: if it fails, stop and correct it before work continues.
Sign-off
Inspected by
Lifting supervisor
Legal basis and references
- [1] United States: OSHA 29 CFR 1910.184, Slings — (c): safe operating practices and identification markings; (d): daily inspection before use by a competent person; (e): chain slings (marking, attachments, 12-month periodic inspection, wear, hooks); (f): wire rope slings (marking, temperature, removal criteria); (h): fibre rope slings; (i): synthetic web slings (marking, chemicals, temperature, repairs, removal criteria).
- [2] United States: OSHA 29 CFR 1926.251, Rigging equipment for material handling — (a): inspection before each shift, markings, removal from the work area when not in use, daily sling inspection; (b): chain attachments and makeshift fasteners; (c): wire rope splices and eyes; (e): web sling marking; (f): shackle and hook working loads.
- [3] Türkiye: İş Ekipmanlarının Kullanımında Sağlık ve Güvenlik Şartları Yönetmeliği (Resmî Gazete, 25.04.2013) — Art. 7: periodic inspection by authorised persons, records, EKİPNET number; Annex I 3.2.2–3.2.2.1: marking of maximum load and of accessories; Annex II 3.1.2–3.1.5: lifting people, no one under loads, selection and storage of accessories; Annex III 1.3: operator checks before work; Annex III Table 2: accessories (slings, clamps, vacuum and magnetic lifters) yearly unless the standards set another interval.
- [4] United Kingdom: HSE: Thorough examination and inspection of lifting equipment (LOLER) — Thorough examination of lifting accessories every 6 months unless an examination scheme sets other intervals; pre-use checks on chains and slings; defects reported and equipment not used until remedied. Marking of SWL and accessory characteristics: HSE LOLER overview page.
Fill in this checklist on your phone. Scan to download FindRisk: run the checklist, add photos, score risks and share a PDF report in minutes.
This form was customized by its user from a FindRisk template. It is a guide and does not replace a risk assessment or the periodic inspection by a competent person.
Based on the template at: findrisk.net/checklists/lifting-accessories-inspection-checklist/ · Version 1