Sling Inspection Checklist: Pre-Use Lifting Accessory Checks
- Frequency
- Before each use
- Completed by
- Rigger, slinger or designated competent person
- Approved by
- Lifting supervisor
- The checklist
- 32 checks · 5 sections
A sling inspection checklist is the check the rigger, slinger or other competent person completes before each use of a sling or other lifting accessory: the identification marking and examination record, a visual check of the sling and its hooks, links and shackles against the removal criteria for its type (chain, wire rope, synthetic or fibre rope), and the rigging of the load. Any accessory that fails a critical check is removed from service at once.
In the United States, OSHA 29 CFR 1910.184(d) requires each sling and all its fastenings and attachments to be inspected each day before use by a competent person designated by the employer; 1926.251 sets the same for construction. In Great Britain, HSE's LOLER guidance expects pre-use checks on slings and chains and a thorough examination of lifting accessories every 6 months unless an examination scheme sets other intervals. In Türkiye, the Work Equipment Regulation requires operator checks before each start of work, marking of accessories, and a periodic inspection of slings and other accessories by an authorised person, yearly unless the standards set another interval.
This form does not replace that periodic inspection or thorough examination, or the plan for the lift. For the wider site, see our construction site safety inspection checklist.
How to use this checklist
- Complete one form per accessory or matched set before it is used, and check again during the job where heat, chemicals or sharp loads could damage it.
- Read the tag first: no legible marking or an overdue examination means the accessory is not used.
- Do the general checks on every item, then only the block for its type, marking the other type blocks N/A.
- Check the rigging against the load: the capacity at the hitch and leg angle you will use, the weakest component, and edge protection.
- If a critical check fails, take the accessory out of service, tag or quarantine it so no one picks it up, and report it in writing.
- Keep the signed form with the lift records and store the accessories where they cannot be damaged.
The checklist: Sling Inspection Checklist: Pre-Use Lifting Accessory Checks
Inspection details
Identification and records
- 1.
The accessory carries a legible tag or marking showing its rated capacityCritical
No legible marking means the accessory is not used.
PassFailN/A - 2.
The marking shows the details needed for its type
Chain: size, grade, rated capacity, reach. Wire rope: safe working load for the hitch, the angle it is based on, number of legs. Synthetic web: rated capacity per hitch and the material.
PassFailN/A - 3.
The latest periodic inspection or thorough examination is recorded and not overdueCritical
Türkiye: authorised person, yearly unless the standards set another interval. UK: thorough examination every 6 months unless an examination scheme says otherwise. US: chain slings at least every 12 months, with a record.
PassFailN/A
Visual checks for every accessory
- 4.PassFailN/A
- 5.
The sling legs are not kinkedCritical
Ref.: [1]
PassFailN/A - 6.
Hooks have no cracks, and are not opened out or twistedCritical
OSHA removes hooks opened more than 15% of the normal throat opening (narrowest point) or twisted more than 10° from the plane of the unbent hook. A safety latch, where fitted, should close the opening.
Ref.: [1]
PassFailN/A - 7.
Master links, coupling links, end fittings, shackles and eyebolts have no cracks, bending or other deformationCritical
The daily check covers the sling and all its fastenings and attachments. Shackles must also show their working load limit.
PassFailN/A - 8.
There is no sign of heat damage (discolouration, melting, charring)Critical
OSHA limits: chain slings removed if heated above 1000 °F; fibre-core wire rope above 200 °F; nylon and polyester webbing not used above 180 °F.
Ref.: [1]
PassFailN/A
Checks by accessory type
Complete only the block for the accessory's type and mark the others N/A.
- 9.
Chain: no cracked, deformed or stretched links and no defective weldsCritical
Lay the chain out straight and look along it for links that are longer, bent or nicked.
Ref.: [1]
PassFailN/A - 10.
Chain: link wear is within the allowed limitCritical
OSHA Table N-184-1 gives the minimum size at any point of a link (e.g. 25/64 in for 1/2 in chain). Otherwise use the manufacturer's wear limits.
PassFailN/A - 11.
Wire rope: fewer than 10 broken wires in one rope lay and fewer than 5 in one strand in one layCritical
Removal criterion in OSHA 1910.184(f)(5)(i): ten randomly distributed broken wires in one rope lay, or five broken wires in one strand in one rope lay.
Ref.: [1]
PassFailN/A - 12.
Wire rope: outside wires are not worn or scraped by a third of their original diameterCritical
Ref.: [1]
PassFailN/A - 13.
Wire rope: no kinking, crushing, bird caging or other distortion of the ropeCritical
Ref.: [1]
PassFailN/A - 14.
Wire rope: no corrosion of the rope or its end attachmentsCritical
Ref.: [1]
PassFailN/A - 15.
Wire rope: eyes are not formed with wire rope clips or knots, and protruding strand ends at splices are covered or bluntedCritical
Ref.: [2]
PassFailN/A - 16.
Synthetic sling: no snags, punctures, tears or cutsCritical
For round slings, also check the cover and follow the manufacturer's discard criteria.
Ref.: [1]
PassFailN/A - 17.
Synthetic sling: no broken or worn stitchesCritical
Ref.: [1]
PassFailN/A - 18.
Synthetic sling: no acid or caustic burnsCritical
Nylon is not used near acids or phenolic fumes; polyester and polypropylene not near caustics.
Ref.: [1]
PassFailN/A - 19.
Fibre rope: no abnormal wear, broken or cut fibres, powdered fibre between strands, uneven strands, discolouration or rotCritical
Repaired or reconditioned fibre rope slings are not used.
Ref.: [1]
PassFailN/A
Rigging the load
- 20.
The accessory suits the load, its lifting points, the connecting parts and the conditions (heat, chemicals, weather)Critical
PassFailN/A - 21.
The load is within the capacity marked for the hitch and leg angle being usedCritical
Capacity changes with the hitch (straight, choke, basket) and falls as the leg angle widens; read the value for this configuration.
PassFailN/A - 22.
Hooks, rings, links and shackles in the set are rated at least as high as the sling, or the set is used at its weakest part's ratingCritical
PassFailN/A - 23.
The sling is padded or protected where it passes over sharp edges of the loadCritical
Ref.: [1]
PassFailN/A - 24.
The sling is securely attached and basket hitch loads are balanced so they cannot slipCritical
Ref.: [1]
PassFailN/A - 25.
Hands and fingers are kept out from between sling and load while the sling is tightened
Ref.: [1]
PassFailN/A - 26.
No one is under the load or in its path, and loads will not pass over unprotected workplacesCritical
PassFailN/A - 27.
The accessory is not used to lift people unless it is provided for that purposeCritical
Ref.: [3]
PassFailN/A - 28.
The load will be taken up without shock loading, and the sling will not be pulled from under a resting load
PassFailN/A
Result
- 29.YesNoN/A
- 30.
Any accessory that failed a critical check has been removed from service and tagged or quarantinedCritical
Do not repair slings on site: OSHA allows repairs only by the manufacturer or an equivalent entity, and bans repaired fibre rope slings.
YesNoN/A - 31.
After use, accessories are stored where they cannot be damaged and are kept out of the immediate work area
PassFailN/A - 32.
Notes and defects found
Note: ________
Critical check: if it fails, stop and correct it before work continues.
Sign-off
Inspected by
Lifting supervisor
Run this checklist on your phone
FindRisk turns inspections into a few taps: AI-generated checklists you can edit and save as templates, photo markup with AI hazard analysis, Fine-Kinney risk scoring and an instant PDF report.
Download FindRiskLegal basis and references
- [1] United States: OSHA 29 CFR 1910.184, Slings — (c): safe operating practices and identification markings; (d): daily inspection before use by a competent person; (e): chain slings (marking, attachments, 12-month periodic inspection, wear, hooks); (f): wire rope slings (marking, temperature, removal criteria); (h): fibre rope slings; (i): synthetic web slings (marking, chemicals, temperature, repairs, removal criteria).
- [2] United States: OSHA 29 CFR 1926.251, Rigging equipment for material handling — (a): inspection before each shift, markings, removal from the work area when not in use, daily sling inspection; (b): chain attachments and makeshift fasteners; (c): wire rope splices and eyes; (e): web sling marking; (f): shackle and hook working loads.
- [3] Türkiye: İş Ekipmanlarının Kullanımında Sağlık ve Güvenlik Şartları Yönetmeliği (Resmî Gazete, 25.04.2013) — Art. 7: periodic inspection by authorised persons, records, EKİPNET number; Annex I 3.2.2–3.2.2.1: marking of maximum load and of accessories; Annex II 3.1.2–3.1.5: lifting people, no one under loads, selection and storage of accessories; Annex III 1.3: operator checks before work; Annex III Table 2: accessories (slings, clamps, vacuum and magnetic lifters) yearly unless the standards set another interval.
- [4] United Kingdom: HSE: Thorough examination and inspection of lifting equipment (LOLER) — Thorough examination of lifting accessories every 6 months unless an examination scheme sets other intervals; pre-use checks on chains and slings; defects reported and equipment not used until remedied. Marking of SWL and accessory characteristics: HSE LOLER overview page.
Version 1 · Updated November 19, 2026 · findrisk.net/checklists/lifting-accessories-inspection-checklist/
Fill in this checklist on your phone. Scan to download FindRisk: run the checklist, add photos, score risks and share a PDF report in minutes.
Version 1 · Updated November 19, 2026 · findrisk.net/checklists/lifting-accessories-inspection-checklist/
Frequently asked questions
How often do slings need to be inspected?
OSHA 1910.184(d) requires a check each day before use by a competent person, with more checks during use where conditions warrant. Alloy chain slings also need a thorough periodic inspection at least every 12 months, with a record of the month it was done. HSE expects lifting accessories to be thoroughly examined every 6 months unless an examination scheme says otherwise; in Türkiye, Table 2 of the Work Equipment Regulation sets a yearly periodic inspection unless the standards set another interval.
When must a wire rope sling be removed from service?
OSHA 1910.184(f)(5) lists ten randomly distributed broken wires in one rope lay or five in one strand in one lay, wear or scraping of one-third of the original diameter of outside wires, kinking, crushing or bird caging, heat damage, cracked, deformed or worn end attachments, opened or twisted hooks, and corrosion of the rope or end attachments. Any one of them means the sling is removed immediately.
When should a synthetic web sling be discarded?
OSHA 1910.184(i)(9) removes web slings with acid or caustic burns, melting or charring, snags, punctures, tears or cuts, broken or worn stitches, or distorted fittings. Temporary repairs are prohibited; repairs are made only by the manufacturer or an equivalent entity and proof tested. For round slings, also follow the manufacturer's discard criteria.
What must be marked on a sling?
OSHA 1910.184(c)(14) bans slings without affixed, legible identification. Chain slings show size, grade, rated capacity and reach; wire rope slings show the safe working load for the hitch, the angle it is based on and the number of legs; web slings show the rated capacity for each hitch and the material. HSE and the Turkish regulation (Annex I 3.2.2.1) also require accessories to be marked with the characteristics needed for safe use.
Who is allowed to inspect lifting accessories?
Under OSHA 1910.184(d), the daily check is done by a competent person designated by the employer. HSE notes that pre-use checks are often made by the user, while thorough examinations are made by a competent person. In Türkiye, periodic inspections are made by authorised persons (yetkili kişi) and the report shows their EKİPNET registration number.